is there a write-up to upgrade from grizzly to havana trunk? what's the right procedure?

edit retag flag offensive close merge delete

2 answers

Sort by ยป oldest newest most voted

answered 2014-02-21 11:08:04 -0500

annegentle gravatar image

We have recently added a section about upgrades and fully documented grizzly to havana upgrades at .

edit flag offensive delete link more


OpenStack needs warm upgrade support! And we have to admit, that many current OpenStack implementations which run on Grizzly have serious problems to upgrade and this will be hopefully addressed in the release after Icehouse by some OpenStack Distros such as RDO, RHOSP, Juju, etc.

cloudssky gravatar imagecloudssky ( 2014-02-21 16:00:35 -0500 )edit

answered 2013-08-31 09:00:13 -0500

dtroyer gravatar image

Upgrade docs are generally not written until release time. However, the upgrade process is tested in the CI gate using Grenade [1] which steps through an upgrade of DevStack from stable/grizzly to master. The upgrade-* scripts in Grenade perform the actual work and show what is required to upgrade the DevStack configuration used in the gate tests. Grenade currently includes Cinder, Glance, Keystone, Nova and Swift.


edit flag offensive delete link more


I thought Grenade is only used for testing. Is it meant to be run against a production server?

rahmu gravatar imagerahmu ( 2014-02-23 17:54:05 -0500 )edit

Your Answer

Please start posting anonymously - your entry will be published after you log in or create a new account.

Add Answer

[hide preview]

Get to know Ask OpenStack

Resources for moderators

Question Tools



Asked: 2013-08-28 15:08:20 -0500

Seen: 944 times

Last updated: Feb 21 '14